Mountain West Technologies - Casper Datacenter Required Power Maintenance (MWT-TID: 61677) – Maintenance details

Casper Datacenter Required Power Maintenance (MWT-TID: 61677)

Completed
Scheduled for November 03, 2023 at 2:00 AM – 2:32 AMUTC

Affects

Updates
  • Completed
    November 03, 2023 at 2:32 AMUTC
    Completed
    November 03, 2023 at 2:32 AMUTC

    Our engineering team as successfully migrated sources and verified power load. Services are now back on normal redundancy connections.

  • In progress
    November 03, 2023 at 2:00 AMUTC
    In progress
    November 03, 2023 at 2:00 AMUTC

    Maintenance is now in progress

  • Planned
    November 03, 2023 at 2:00 AMUTC
    Planned
    November 03, 2023 at 2:00 AMUTC

    To ensure stability and redundancy of our colocation power systems, we will be transferring our datacenter backup power load to UPS 4-1-2 from 4-1-1.

    During this time we will pre-load backup power sources in case of a fault during the transfer, or a commercial power failure during this time. This maintenance is required, and considered a moderate risk to service.